Kampala Metropolitan Transmission System Improvement Project

Status

Under Implementation

Project Background

Given the rapid power demand growth in the Greater Kampala Metropolitan Area (GKMA), it became clear that the existing transmission network would, in the near future, be unable to adequately support the increasing demand for reliable and stable power supply.

Recognizing this need, the Government of Uganda through its implementing agency, UETCL, undertook the Kampala Metropolitan System Improvement Project.

Objective

To improve the Greater Kampala Metropolitan Area (GKMA) transmission system to meet the growing power demand in the area. This will be achieved by enhancing the capacity of substations and reducing power outages in the GKMA, the heart of Uganda’s economic growth and development.

Lot 1

Activity Component Contractor
  • Construction of Buloba substation and associated transmission lines

 

  • Construction of Buloba substation
  • Upgrade of Mutundwe substation
  • Upgrade of Bujagali substation
  • Consortium of Toyota Tsusho Engineering Corporation and China Machinery Engineering Corporation

Lot 2

Activity Component Contractor
  • Construction of New Mukono Substation and associated Transmission Lines, Upgrading of Kawaala Substation, and Reconductoring Works
  • Construction of new Mukono substation
  • Upgrade of Kawaala substation
  • Reconductering of 132kV lines
  • Consortium of Toyota Tsusho Engineering Corporation and China Machinery Engineering Corporation

Lot 3

Activity Component Contractor
  • Procurement of mobile substation
  • Procurement of mobile substation
  • PT. Elswedy Electric Indonesia

Financier

  1. JICA

Project Status

Lot 1

Component Status
  • Buloba substation
  • Bujagali substation
  • Mutundwe substation
  • Buloba 220kV transmission line
  • Buloba 132kV transmission line

 

  • 100%
  • 99%
  • 94%
  • 100%
  • 100%
Overall progress 98.9%

Lot 2

Component Status
  • New Mukono substation
  • Namungoona substation
  • 220kV Mukono North transmission line connection
  • 132kV Mukono North transmission line connection
  • 132kV Namungoona transmission line connection
  • 132kV transmission line reconductering

 

  • 97%
  • 76%
  • 94%
  • 94%
  • 63%
  • 71%
Overall progress 83.74%

Lot 3

  • Mobile substation was procured and energized. Currently based at Namungoona.

Status of Resettlement Action Plan (RAP) Implementation

  • 97%

Progress Reports