Project

Kampala Metropolitan Transmission System Improvement Project

Status

Under Implementation

Contract Details

Lot 1 New Buloba SS, Mutundwe & Bujagali upgrade, Reconductoring of 132 kV Lines:
Contractor: Consortium of Toyota Tsusho Engineering Corporation and China Machinery Engineering Corporation

Lot 2 New Mukono Substation, upgrade of Kawaala:
Contractor: Consortium of Toyota Tsusho Engineering Corporation and China Machinery Engineering Corporation

Lot 3 Mobile substation:
Contractor: PT. ELSEWEDY ELECTRIC INDONESIA

Financier(s)

  1. JICA

Overall Status/ Physical Performance – LOTS 1 & 2

  • The contracts for Lot 1 (Construction of Buloba Substation and associated Transmission Lines and Upgrading of Mutundwe and Bujagali Substations) and Lots 2 Construction of New Mukono Substation and associated Transmission Lines, Upgrading of Kawaala Substation, and Reconductoring Works) were signed on 7th August 2023.
  • The EPC Contractor received the full advance payment for both lots on 14th December 2023.
  • Renewed ESIA certificate was obtained from NEMA on 9th February 2024.
  • The official commencement date is 12th February 2024.
  • Submission and review of designs is ongoing.

Overall Status/ Physical Performance – LOTS 3

  • Contract for Lot 3 – Supply of the multi-ratio mobile substation (132/33-11kV, 20MVA) was signed on 19 May 2023.
  • Design is 83% complete.
  • Manufacturing of the Equipment is in progress and estimated at 39% completion.
  • FAT for the power transformer is scheduled for 22nd – 25th April 2024.

RoW acquisition progress

  • RAP Implementation is 92% (130 out of 141) complete.