Tororo-Lira 132kV Transmission Project

Project Name

Tororo-Opuyo-Lira 132kVĀ  Transmission Project

Objectives

  • To evacuate electricity from upcoming power plants and to improve electricity access, lower transmission losses, increase power efficiency, reliability, stability and quality of supply to consumers in the country especially the western and North Eastern regions

Financing

  • African Development Bank (ADB)
  • Government of Uganda

Status

  • Construction is 95% complete
  • 115.5km Opuyo-Lira section was energized on 16th April, 2020
  • Opuyo to Mbale was completed and energized on 16th April 2020
  • Tororo to Mbale still under construction