Gulu-Agago 132kV Transmission Line and Associated Substations Project

Status

Under Implementation

Contract Details

Contract Details (Lot A Substations):
Contractor: Larsen & Toubro Limited (L&T)

Contract Details (Lot B Transmission Line):
Contractor: KEC International Limited (KEC)

Financier(s)

  1. German Government though Kreditanstalt für Wiederaufbau (KfW)

Overall Status/ Physical Performance

  • The overall progress of construction of the project is 100%.
  • The transmission line was successfully energized on 18th November 2023.
  • The extension bays at Gulu substation and Agago HPP switchyard were successfully energized on 18th November 2023.
  • Commissioning of the project took place at new Agago 132/33kV substation on 21st February 2024.
  • Completion of outstanding works at Agago substation is scheduled to be completed by 31st March 2024.

RoW acquisition progress

  • RAP Implementation is 98.9% complete (468 out of 473 PAPs have been paid)
  • The outstanding cases are being handled on a case-by-case basis.