Project

Completion of Installation works of 220kV Overhead transmission line for the Interconnection of Uganda-Kenya Electric Grids – Lot A

Status

Under Implementation

Construction Progress

Construction of the 131km Bujagali – Tororo 220kV double circuit transmission line is 70% complete with detailed progress as follows:

  • Foundation construction is at 77% (310/402);
  • Tower Erection is at 61.4% (247/402);
  • Stringing is at 26% (33.9/131.2km).

Financier(s)

  1. Government of Uganda

RoW acquisition progress

  • RAP Implementation is 97% complete i.e., 3,097 out of 3,199 PAPs have been paid.