No. Project Objective Status
1 Muzizi Interconnection: (2×90 MVA
220/132/33kV Muzizi Substation)
Provision of transmission capacity to evacuate power from Muzizi Hydro Power Plant (HPP) Sourcing for financing for implementation
2 Ayago Interconnection Project Provision of Transmission capacity to evacuate power from Ayago Hydro Power Plant (HPP) At Feasibility Study/ Project Proposal Stage

 

3 37.3km 132kV Mirama-Kikagati-Nsongezi Provision of transmission capacity to evacuate power Likely investor carrying out technical designs
4 45km 220kV Hoima-Kinyara Provision of transmission capacity to evacuate power Sourcing for Financing for EPC
5 74km 132kV Mbale – Bulambuli – Kapterol Transmission Line Provision of transmission capacity to evacuate power from IPPs in Bulambuli area Feasibility Study completed
6 Extension of Transmission Grid to Evacuate excess electricity generated from Tilenga and Kingfisher oil fields Provision of transmission capacity to evacuate power from Tilenga and King Fisher Oil Fields Design revisited together with developer
7 Nkenda Substation 132/33kV Upgrade (2X60MVA 132/33kV Transformers) Increase Substation Capacity Sourcing for Financing for Implementation
8 183km, 132kV single circuit Agago – Lira

Transmission Line

Provision of transmission

capacity to evacuate power from Agago 42 MW HPP

Sourcing for financing for Interim solution
9 400kV Oriang Interconnection project Provision of transmission

capacity to evacuate power from Oriang HPP

Sourcing for Financing
10 400kV Kiba Interconnection Project Provision of transmission

capacity to evacuate power from Kiba HPP

Sourcing for Financing