Kampala Entebbe Expansion Project
Project Name
Kampala-Entebbe Expansion Project
Objectives
- To provide transmission capacity to supply reliable and quality power to Entebbe town and surrounding areas
Scope
- The construction of 23.8km, 132kV double circuit Mutundwe – Entebbe Transmission line.
- Extension of Mutundwe 132/33/11kV substation
Financier(s)
- KfW Bank – German Development Bank
- Government of Uganda
RAP Implementation Status: 82%
- 866 of 1,053 Project Affected Persons have been compensated