Mirama Kabale Transmission Project

Project Name

Mirama-Kabale 132kV transmission project

Objectives
  • To boost the existing transmission capacity of 33kV to enable provision of reliable, quality and adequate power supply to Kigezi sub region situated in the southern part of Uganda.
Scope
  • Construction of 132kV (85km) transmission line and related substation extension at Mirama
  • Related substation extension at Mirama
  • New substation at Kabale
Financier(s)
  • Islamic Development Bank
  • Government of Uganda
Status: 63%
  • 184 of 294 tower foundations completed
  • 83 of 294 towers erected