Mbarara-Nkenda 132kV Transmission Project

Project Name

Mbarara-Nkenda 132kV Transmission Project

Scope

  • Construction of 160km, 132kV, Double Circuit Mbarara-Nkenda Transmission Line
  • Associated substations.

Objectives

  • To expand and strengthen the national transmission grid and boost economic growth in western Uganda.
  • To evacuate electricity from upcoming power plants and to improve electricity access, lower transmission losses, increase power efficiency, reliability, stability and quality of supply to consumers in the country especially the western region.

Financier(s)

  • African Development Bank (AfDB)
  • Government of Uganda

RAP Implementation Status: 94%

  • 1,709 of 1,815 project affected persons have been compensated.

 

 