Plot No.10, Hannington Rd, Kampala

info@uetcl.com

Image Alt
  /  Projects   /  Under RAP Implementation   /  Lira-Gulu-Agago 132kV transmission project

Lira-Gulu-Agago 132kV transmission project

Project Name

Lira-Gulu-Agago 132kV transmission line & associated substations

Objectives

  • To provide transmission capacity to evacuate power from Agago/Achwa 88MW power plant
  • To reinforce supply to the Northern and West Nile region, and to meet the regions un-served demand

Financier(s)

  • German Development Bank (KfW)
  • Government of Uganda

RAP Implementation Status

  •  No. of Project Affected Persons: 1, 459
  • No. of payments: 1,337
  • Disputes: 6   