Electrification of Industrial Parks

Scope

  • Luzira Industrial Park 132/133kV Substation and transmission Line Project (15km)
  • Mukono Industrial Park 132/133kV Substation and Transmission Line Project (5km)
  • Iganga Industrial Park 132/133kV Substation and Transmission Line Project (10x2km)
  • Namanve Industrial Park 132/133kV Substation and Transmission Line Project (5km)

Objectives

  • Provision of adequate transmission capacity to cater for projected demand within industrial areas

Financiers

  • China Export Import (EXIM) Bank
  • Government of Uganda

Status

  • Namanve North-Namanve South commissioned on 26th January 2021
  • Iganga Transmission Line commissioned on 8thDecember2019
  • Mukono Transmission Line commissioned on 4thJuly, 2019
  • Namanve South-Luzira – 38%thDecember2019