Mbarara-Nkenda 132kV Transmission Project
Project Name Mbarara-Nkenda 132kV Transmission Project Scope Construction of 160km, 132kV, Double Circuit Mbarara-Nkenda Transmission Line Associated substations. Objectives To expand and strengthen the national transmission grid and boost economic growth in western Uganda. To evacuate electricity from upcoming power plants and to
Interconnection of Electric Grids of Nile Equatorial Lakes Countries
Project Name Interconnection of Electric Grids of Nile Equatorial Lakes Countries Mbarara-Mirama-Birembo (Rwanda) 220kV transmission line Bujagali-Tororo-Lessos 220kV transmission line Extension of substations at Bujagali, Tororo and Mbarara Construction of a new 220/132/33kV substation at Mirama. Objectives Improve access to electricity in the Nile Basin Initiative (NBI)
Karuma Interconnection Project
Project Name Karuma Interconnection Project Components Karuma-Kawanda 400kV transmission line Karuma-Olwiyo 400kV transmission line Karuma-Lira 132kV transmission line Associated substations Objectives Provision of adequate transmission capacity to evacuate power generated at Karuma 600MW Hydro Power Station (HPS) Financier(s) China EXIM Bank Government of Uganda RAP Implementation status: 88% Project Affected Persons: 3,049 No. of
Grid Expansion and Reinforcement Project: Kole-Gulu-Nebbi-Arua Transmission Project
Project Name Grid Expansion and Reinforcement Project (GERP) Kole-Gulu-Nebbi- Arua 132kV transmission line Objectives To ensure strategic expansion and upgrade of power transmission infrastructure to meet present and future electricity demand in the West Nile region and Northern Uganda Financier(s) World Bank through the International Development
Tororo-Lira 132kV Transmission Project
Project Name Tororo-Lira 132kV transmission line Objectives Improve electricity access, lower transmission losses, increase power efficiency, reliability, stability and quality of supply in the North east region. Evacuate power from upcoming solar fields and other power plants Financier(s) African Development Bank Government of Uganda RAP Implementation Status: 95% 4,424
Kampala Entebbe Expansion Project
Project Name Kampala-Entebbe Expansion Project Objectives To provide transmission capacity to supply reliable and quality power to Entebbe town and surrounding areas Scope The construction of 23.8km, 132kV double circuit Mutundwe - Entebbe Transmission line. Extension of Mutundwe 132/33/11kV substation Financier(s) KfW Bank - German Development Bank Government of