Project Name Interconnection of Electric Grids of Nile Equatorial Lakes Countries Mbarara-Mirama-Birembo (Rwanda) 220kV transmission line Bujagali-Tororo-Lessos 220kV transmission line Extension of substations at Bujagali, Tororo and Mbarara Construction of a new 220/132/33kV substation at Mirama. Objectives Improve access to electricity in the Nile Basin Initiative (NBI)

Project Name Karuma Interconnection Project Components Karuma-Kawanda 400kV transmission line Karuma-Olwiyo 400kV transmission line Karuma-Lira 132kV transmission line Associated substations Objectives Provision of adequate transmission capacity to evacuate power generated at Karuma 600MW Hydro Power Station (HPS) Financier(s) China EXIM Bank Government of Uganda RAP Implementation status: 88% Project Affected Persons: 3,049 No. of

Project Name Grid Expansion and Reinforcement Project (GERP) Kole-Gulu-Nebbi- Arua 132kV transmission line Objectives To ensure strategic expansion and upgrade of power transmission infrastructure to meet present and future electricity demand in the West Nile region and Northern Uganda Financier(s) World Bank through the International Development