Project

Mutundwe Entebbe 132kV Transmission Line and Associated Substations (MEB)

Status

Under Implementation

Contract Details

Contract Details (Lot 1 Transmission Line):
Contractor: National Contracting Company Ltd (NCC)

Contract Details (Lot 2 Substations):
Contractor: Xian Electric Engineering Company Ltd

Financier(s)

  1. German Government though Kreditanstalt für Wiederaufbau (KfW)

Overall Status/ Physical Performance

  • Construction is 100% complete.
  • The transmission line was energized on 11th May 2023.
  • The line is currently under 1-year Defects Liability Period (DLP).
  • Mutundwe substation was energized on 11th May 2023.
  • Entebbe substation energized on 16th May 2023.
  • Three transformers were loaded by 15th July 2023.

RoW acquisition progress

  • RAP Implementation is at 85% (899/1053).
  • The outstanding cases are being handled on a case-by-case basis.