Project

Karuma Interconnection Project (KIP)

Status

Implementation

Contract Details

Contractor: Sino Hydro Corporation Ltd

Financier(s)

  1. Export-Import Bank of China

Overall Status/ Physical Performance

  • The works on the project are 100% Complete.
  • Karuma – Kawanda 248km, 400kV double-circuit transmission line construction was completed. Circuit No. 1 was energized on 28 November 2021 and Circuit No. 2 was energized on 21 March 2022.

RoW acquisition progress

  • RAP Implementation is 90% (3,902 of 4,327 PAPs) complete
  • The outstanding cases are being handled on a case-by-case basis